09/2009 |
Approval of the project and receiving the building permit |
09/2011 |
Start of construction |
12/2012 |
End of construction of the pressing shop, start of installation of technology |
02/2013 |
Installation of the steam boiler and the turbine with the generator |
04/2013 |
Start of operation of the pressing shop |
09/2013 |
End of construction of the power plant |
11/2013 |
Starting the trial run of the power plant |
04/2015 |
Final approval of the power plant, permanent operation |
08/2016 |
Restoration of the boiler of the power plant |